NEM MINIMUM SYSTEM LOAD #145114

Forecast Minimum System Load (MSL1) condition in the SA region on 12/09/2026

Original (nemweb.com.au) AEMO listing
AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 145092 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA region on 12/09/2026.

Minimum System Load (MSL) conditions are forecast when demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
-	MSL1: -40 MW 
-	MSL2: -315 MW 
-	MSL3: -530 MW 

The demand is forecast to be below the MSL1 threshold for the following period: 
From 1300 hrs to 1400 hrs 12/09/2026. Minimum demand is forecast to be -46 MW at 1330 hrs.

Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data .