NEM
INTER-REGIONAL TRANSFER
#144971
Inter-regional transfer limit variation - Tungatina 110 kV Substation - TAS region - 02/09/2026
AEMO ELECTRICITY MARKET NOTICE Inter-regional transfer limit variation - Tungatina 110 kV Substation - TAS region - 02/09/2026 At 2100hrs 02/09/2026 there was an unplanned outage of Tungatina 110 kV Substation. The following constraint set(s) invoked at 2140 hrs 02/09/2026 T-PMWA This constraint set(s) contains equations with the following interconnectors on the LHS. T-V-MNSP1 Refer to the AEMO Network Outage Scheduler for further information. Manager NEM Real Time Operations