Market Notices
NEM INTER-REGIONAL TRANSFER #144887

Inter-regional transfer limit variation - Sydney West - Vineyard No. 29 330 kV Line - NSW region - 19/08/2026

Original (nemweb.com.au) AEMO listing
AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Sydney West - Vineyard No. 29 330 kV Line - NSW region - 19/08/2026

At   1530 hrs 19/08/2026 there was an unplanned outage of Sydney West - Vineyard No. 29 330 kV Line.

The following constraint set(s) invoked at 1550 hrs 19/08/2026
N-SWVY_29

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
  
Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations