NEM
INTER-REGIONAL TRANSFER
#146502
Inter-regional transfer limit variation - Upper Tumut-Stockdill 1 330kV line - NSW region - 19/11/2026
AEMO ELECTRICITY MARKET NOTICE Inter-regional transfer limit variation - Upper Tumut-Stockdill 1 330kV line - NSW region - 19/11/2026 At 1912 hrs 19/11/2026 there was an unplanned outage of Upper Tumut-Stockdill 1 330kV line. The following constraint set(s) invoked at 1925 hrs 19/11/2026 N-SDUT_1 This constraint set(s) contains equations with the following interconnectors on the LHS. NSW1-SA1,VIC1-NSW1,V-S-MNSP1 Refer to the AEMO Network Outage Scheduler for further information. Manager NEM Real Time Operations