Market Notices
NEM GENERAL NOTICE #145435

NSW to SA (Project Energy Connect) Interconnector Registered - 01/10/2026

Original (nemweb.com.au) AEMO listing
AEMO ELECTRICITY MARKET NOTICE
 
The New South Wales to South Australia (Project Energy Connect) interconnector has been registered in AEMO's market systems with effect from 00:00 hrs AEST on 1 October 2026. The ID of this interconnector is NSW1-SA1.
 
The capacity of this interconnector is +/- 150 MW. Currently the line 6F (Bundey to Buronga) is out of service - this is planned to return to service at 1200hrs 1 October. Refer to NOS for updates for this outage. When the line is returned to service the loop flow constraints will be active in the set L-PEC_X_6C_6G_6H.
 
For more information refer to the PEC project page on AEMO's website:
 
Go live plan:
https://www.aemo.com.au/-/media/files/initiatives/project-energyconnect/implementation-toolbox/pec-mi-final-industry-go-live-plan
 
PEC project webpage: 
https://www.aemo.com.au/initiatives/major-programs/nem-reform-program/nem-reform-program-initiatives
 
Manager NEM Real Time Operations