NEM
GENERAL NOTICE
#145435
NSW to SA (Project Energy Connect) Interconnector Registered - 01/10/2026
AEMO ELECTRICITY MARKET NOTICE The New South Wales to South Australia (Project Energy Connect) interconnector has been registered in AEMO's market systems with effect from 00:00 hrs AEST on 1 October 2026. The ID of this interconnector is NSW1-SA1. The capacity of this interconnector is +/- 150 MW. Currently the line 6F (Bundey to Buronga) is out of service - this is planned to return to service at 1200hrs 1 October. Refer to NOS for updates for this outage. When the line is returned to service the loop flow constraints will be active in the set L-PEC_X_6C_6G_6H. For more information refer to the PEC project page on AEMO's website: Go live plan: https://www.aemo.com.au/-/media/files/initiatives/project-energyconnect/implementation-toolbox/pec-mi-final-industry-go-live-plan PEC project webpage: https://www.aemo.com.au/initiatives/major-programs/nem-reform-program/nem-reform-program-initiatives Manager NEM Real Time Operations