Inter-regional transfer limit variation - Mt Piper-Wollar 5A5 500kV line - NSW region - 29/09/2026
AEMO ELECTRICITY MARKET NOTICE Inter-regional transfer limit variation - Mt Piper-Wollar 5A5 500kV line - NSW region - 29/09/2026 A planned outage of Mt Piper-Wollar 5A5 500kV line in the NSW region was scheduled from 0600 hrs 25/09/2026 to 1800 hrs 02/10/2026. The outage has been completed and Mt Piper-Wollar 5A5 500kV line returned to service at 1605 hrs 29/09/2026 Constraint set revoked: N-MPWO_5A5 Manager NEM Real Time Operations