Market Notices
NEM RESERVE NOTICE #144345

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2026

Original (nemweb.com.au) AEMO listing
AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 0800 hrs 03/07/2026 to 1000 hrs 03/07/2026. 
The forecast capacity reserve requirement is 386 MW. 
The minimum capacity reserve available is 346 MW.

[2.] From 1600 hrs 03/07/2026 to 0000 hrs 04/07/2026. 
The forecast capacity reserve requirement is 360 MW. 
The minimum capacity reserve available is 324 MW.

Manager NEM Real Time Operations