NEM
INTER-REGIONAL TRANSFER
#144283
Inter-regional transfer limit variation - X3 Balranald- Buronga 220kV line - NSW region - 20/06/2026
AEMO ELECTRICITY MARKET NOTICE Inter-regional transfer limit variation - X3 Balranald- Buronga 220kV line - NSW region - 20/06/2026 At 1210 hrs 20/06/2026 there was a short notice rating change of X3 Balranald- Buronga 220kV line Constraint set(s) invoked: CA_SYDS_594882A3 The constraint sets contain equations with the following interconnectors on the LHS. V-SA V-S-MNSP1 Refer to the AEMO Network Outage Scheduler for further information. Manager NEM Real Time Operations