NEM
RECLASSIFY CONTINGENCY
#144045
Cancellation of a Non-Credible Contingency Event: Sheffield - George Town 1 & 2 220kV line and line in TAS1 due to Lightning.
AEMO ELECTRICITY MARKET NOTICE Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event. Region: TAS1 Lines: Sheffield - George Town 1 & 2 220kV and Cancellation time: 05/05/2026 00:04 Constraint set(s) revoked: T-GTSH_N-2 Constraint set contains the following interconnector(s) on the left hand side: T-V-MNSP1 Refer AEMO Electricity Market Notice 144038 Auto-generated on behalf of Manager NEM Real Time Operations